Construction Update at Harbourside Place

September 16, 2011

The construction crew has made substantial progress on this phase since the last update, with construction of the seawall at Harbourside Place almost complete.  They have one final pour of 250 linear feet of concrete left and look to have this in place and cured by the end of next week.  Today, the crew installed 10 timber pilings for the dock and look to have all piling installations completed by the end of next week.  They will then look to complete the dock system by installing the joists and stringers. Photos and descriptions follow below.

The final bulkhead cap has been poured on more than 75% of the seawall for Harbourside Place
The crew continues to install timber pilings for the new marina at Harbourside Place
Crews continue to work on the new roadway for the anticipated rise in traffic for Harbourside Place
View of the project from the Indiantown drawbridge

View of the project from the other side of the Intracoastal Waterway